Electrical Permit in Cambridge, MA

Permit Summary

Permit status
Permit required
Official permit name
Electrical Permit
Fee
Cambridge uses an itemized electrical/wiring fee schedule rather than one general permit price. Examples include new service or service work at $10 per 100 amps, residential low-voltage control wiring at $25 and commercial at $100, residential alarm systems at $25 and commercial at $75, photovoltaic arrays at $100 per array, a $50 reinspection fee for code violations, and a $100 shutdown fee plus the inspection fee. Work started before obtaining a required permit is charged triple the specified permit fee; other applicable item charges may apply.
Processing time
Cambridge does not publish a fixed electrical-permit review target on its current electrical permit and application pages. Under M.G.L. c. 143, § 3L, after written notice that the electrical work is complete, the inspector of wires must give written approval or disapproval within five days.
Inspection required
Yes

Who Can Do the Electrical Work?

Homeowner work allowed
No
Licensed contractor required
Yes

Homeowner Eligibility Rules

Cambridge states that wiring permits are issued to Massachusetts-licensed electricians and does not publish an unlicensed homeowner exception for electrical permits. A property owner who is not appropriately licensed therefore cannot use the Cambridge wiring-permit process to perform the permitted electrical work personally.

Contractor Rules

The permit is issued to a Massachusetts-licensed electrician. The statewide permit form records the firm name and applicable master or systems and journeyman license information; security-system businesses must provide the required Massachusetts S license. The form also requires liability insurance or equivalent coverage unless the owner signs the permitted insurance waiver.

Permit & Plan Review

Electrical Work Covered

Cambridge requires an electrical permit for work performed under 527 CMR 12.00. The current Massachusetts Electrical Code covers installations, repairs, maintenance, and removal of electrical wiring and fixtures used for light, heat, power, signaling, and communications in covered buildings and structures.

Plan Review Rules

Cambridge states that Electrical/Wiring Inspectors review and approve electrical permit applications, and the statewide permit form allows additional detail to be required by the Inspector of Wires. Current Cambridge electrical guidance does not publish a separate formal electrical plan-review threshold or standard drawing set for ordinary wiring permits.

Service, Panel & Utility Requirements

Utility coordination required
Sometimes

Service / Panel Rules

Service and panel work is subject to the electrical permit and inspection process. Cambridge's fee schedule charges new service and service work by amperage and states that all service equipment greater than 1,000 amps must be tested by a certified testing firm. New or upgraded service also requires coordination with the serving electric utility.

Service Reconnect Rules

For customer-owned service equipment that has been repaired after damage or disconnection, Eversource instructs the customer or electrician to contact the local wire inspector before Eversource restores service. Cambridge's fee schedule separately lists a shutdown charge of $100 plus the applicable inspection fee.

Low-Voltage Rules

Cambridge's electrical fee schedule expressly includes low-voltage control wiring, data wiring, audio-visual systems, and security and fire alarm systems, so these systems are not treated as a blanket no-permit category. Fire alarm work can also require a separate Cambridge Fire Department fire alarm permit and related building-permit documentation.

Utility Coordination Rules

Coordinate with Eversource when the project changes utility service, including a new service, service upgrade, additional meter, service drop work, or similar utility-side work. Eversource provides construction and renovation work requests for these services. Distributed-generation systems such as solar require the applicable Eversource interconnection process in addition to the local electrical permit.

Inspections & Permit Life

Electrical Inspection Stages

Cambridge states that electrical permits include at least two inspections: rough and final. Under current 527 CMR 12.00, electrical work may not be concealed or covered before inspection; after proper notice, the inspection window is not more than 24 hours for interior or exterior excavations and 72 hours for other interior or exterior installations, excluding Saturdays, Sundays, and holidays. Completion must also be reported to the inspector of wires.

Permit Expiration / Inspection Interval

Under current 527 CMR 12.00 Rule 8, an electrical permit may be deemed abandoned and invalid if the authorized work has not commenced or has not progressed during the preceding 12 months. A written extension must be permitted for reasonable cause. The permit may also be terminated on written request of the owner or the installing entity named on the permit.

What You Need Before Applying

Requirements

Obtain the Electrical Permit through Cambridge Inspectional Services before performing work covered by the Massachusetts Electrical Code. Cambridge issues wiring permits to Massachusetts-licensed electricians. Work must comply with the current 527 CMR 12.00 Massachusetts Electrical Code, and required inspections must be requested before wiring is concealed and at completion. Service work may also require utility authorization or coordination.

Exemptions

Cambridge's electrical/wiring fee schedule expressly states that no permit is required for portable room air-conditioning units. The City otherwise states that an electrical permit is required for work performed under the Massachusetts Electrical Code; no general unlicensed-homeowner permit pathway is identified.

Required Documents

Submit the prescribed Massachusetts Application for Permit to Perform Electrical Work through Cambridge's online permitting system. Required application information includes the job location; owner or tenant and contact information; whether the work is tied to a building permit; building use; utility authorization number when applicable; existing and proposed service information; description and quantities of electrical work; estimated value when required; start date; firm and electrician or systems license information; and proof of liability coverage, bond, other qualifying coverage, or an owner insurance waiver. Additional detail may be required by the Inspector of Wires.

How to Apply

Go to Official Application

Official Sources

Last verified: October 6, 2026