Shed Permit in Seattle, WA

Permit Summary

Permit status
Permit may be required
Official permit name
Construction Permit - Subject-to-Field-Inspection; Construction Permit - Addition or Alteration
Fee
2026 construction-permit fees are value-based. The Development Fee Index (DFI) starts at $325 for the first $1,000 of project value and, through $25,000, adds $1.60 per additional $100 or fraction; higher valuation tiers apply above that. A regular building permit charges 100% of DFI for the permit plus 100% of DFI for plan review; an STFI permit charges 100% of DFI for the permit plus 40% of DFI for plan review. The minimum value-based permit or plan-review fee is $292, the minimum STFI plan-review fee is $116.75, and a 5% technology fee applies. Other applicable review or trade fees may apply.
Processing time
SDCI does not publish one fixed shed-wide review timeline. Most permitted sheds qualify for Subject-to-Field-Inspection review; SDCI states that STFI application screening takes a few days, after which the permit is issued once the application is in order and fees are paid. Sheds requiring regular Addition or Alteration review have project-dependent review times.
Inspection required
Sometimes

Do You Need a Shed Permit?

Building permit size threshold
A one-story detached shed may be exempt from a construction permit when its projected roof area does not exceed 120 square feet and all other exemption conditions are met. A shed over 120 square feet does not qualify for that exemption.
Building permit height threshold
The construction-permit exemption is limited to a one-story detached shed; SDCI does not state a separate numeric height threshold for the exemption. Separately, SDCI's shed guidance states that a shed cannot be more than 12 feet tall.

Exemptions

A construction permit is not required only when all of SDCI's shed-exemption conditions are met: the detached shed is one story, its projected roof area is 120 square feet or less, it is supported on a simple slab-on-grade, pier blocks, or soil, it is not attached to another building, it is not in or near an environmentally critical area, and it is used only for storage, growing plants, or similar generally unoccupied purposes. The exemption does not waive other applicable code requirements.

Attached Shed Rules

An attached shed does not qualify for Seattle's no-construction-permit shed exemption. SDCI states that sheds not meeting all exemption conditions require a construction permit; most qualify for the Subject-to-Field-Inspection path unless regular review is triggered.

Shed Use Rules

The construction-permit exemption is limited to storage, growing plants, or similar generally unoccupied uses. A shed intended for occupied or habitable use does not fit the permit-exempt storage-shed pathway and must be reviewed under the applicable use and construction requirements.

Zoning & Placement Rules

Zoning approval may be required
Sometimes

Zoning Rules

Every shed must comply with Seattle land-use rules even when no construction permit is required. In Neighborhood Residential zones, current 2026 standards in SMC Chapter 23.44 govern lot coverage, setbacks, height, and accessory-structure placement. Permitted sheds are reviewed for Land Use Code compliance as part of SDCI review, and site-specific conditions can trigger additional land-use review.

Setback Rules

Under current Neighborhood Residential standards, the front setback is generally 15 feet on lots with one or two dwelling units and 10 feet on lots with three or more dwelling units. Where the rear lot line does not abut an alley, the rear setback is generally 15 feet for lots with one or two dwelling units and 10 feet for lots with three or more; certain other structures on lots under 5,000 square feet within a frequent-transit service area use a 5-foot rear setback, while no rear setback is required where the rear lot line abuts an alley. Side setbacks are generally 5 feet average with a 3-foot minimum, or 3 feet on qualifying lots under 5,000 square feet within a frequent-transit service area. Accessory-structure provisions can allow placement in required rear or side setbacks subject to additional conditions.

Maximum Height Rules

SDCI's current shed guidance states that a shed cannot be more than 12 feet tall. Other zone- or site-specific development standards may also apply.

Lot Coverage Rules

In current Neighborhood Residential zones, structures are generally limited to 50% lot coverage. Up to 60% coverage is allowed only for specified qualifying development, including certain frequent-transit common-amenity projects and stacked dwelling-unit development. A shed must be included in the applicable structure/lot-coverage calculation, and site-specific constraints can further limit development.

Special Area Rules

A shed in or near an environmentally critical area does not qualify for the small-shed construction-permit exemption and requires the Addition or Alteration permit path. Environmentally critical area, shoreline, steep-slope, wetland, and similar site conditions can trigger additional pre-application review, site visits, surveys, geotechnical documentation, or development restrictions.

Construction Requirements

Foundation Rules

For the shed construction-permit exemption, SDCI allows a simple concrete slab-on-grade, pier blocks, or direct support on soil. The Seattle Building Code exemption does not apply when the shed is placed on a concrete foundation other than a slab-on-grade.

Fire Separation Rules

Permit-exempt detached tool or storage sheds that qualify under Seattle Residential Code R105.2 are exempt from location-based exterior-wall protection, but projections may not extend across a lot line. For permitted residential-code sheds, SRC R302.1 fire-separation rules apply; unprotected exterior walls generally require at least 5 feet of fire-separation distance, with fire-resistance, projection, and opening limits applying at shorter distances.

Permit & Review Path

Permit / Review Path

No construction permit is required only when every small-shed exemption condition is met. Otherwise, SDCI states that most sheds can use the Construction Permit - Subject-to-Field-Inspection process. A Construction Permit - Addition or Alteration is required when the shed is in or near an environmentally critical area, is larger than 750 square feet, or has beams spanning more than 14 feet.

Trade Permits & Professional Design

Trade permits required
Sometimes
Professional design required
Sometimes

Trade Permit Rules

Separate trade permits depend on the shed's installed systems. New or altered electrical wiring or equipment generally requires an SDCI electrical permit, and new electrical service or service changes may also require coordination with Seattle City Light. Other trade permits apply when the project includes work regulated under those permit programs.

Professional Design Rules

SDCI states that shed drawings rarely require a professional stamp and that anyone with drafting skills may prepare typical shed plans. A licensed architect or engineer may be required when the project falls outside applicable design-professional exceptions or when SDCI requires engineered construction documents; environmentally critical area conditions can also require specialist reports.

What You Need Before Applying

Requirements

Confirm the site's zoning and environmentally critical area conditions. If a construction permit is required, submit the Building & Land Use Pre-Application through the Seattle Services Portal with the required site and construction information. All sheds, including permit-exempt sheds, must comply with applicable building, land-use, stormwater, grading, and environmentally critical area rules, and separate trade approvals may apply to installed systems.

Required Documents

For a permitted shed, SDCI's construction-permit process generally requires a Building & Land Use Pre-Application, site plan, complete legal description, and scaled plans showing existing conditions and the proposed work. Site-specific or environmentally critical area projects may require additional documentation such as a topographic survey or geotechnical report.

How to Apply

Go to Official Application